4.02.16

Upstairs is finished

19.11.15

Glass floor is laid section by section

17.11.15

Glass beams go in

26.04.14

Main bedroom

25.04.14

Dylan’s bedroom

24.04.14

Spare bedroom

23.04.14

Arched spare bedroom

29.03.14

Back stairs and 1st floor toilet

28.03.14

Back kitchen

12.01.14

Only the glass floors left

10.01.14

Kitchen is finally finished

7.01.14

Issues with the Corian

24.12.13

Christmas upstairs!

20.12.13

Back stairs handrail goes in

14.12.13

Applying the hard wax oil

7.12.13

2nd Corian worktop is fitted

30.11.13

Utility room, units go in and door is finished

15.11.13

Issues with Corian sink

15.11.13

Stainless steel back kitchen worktop arrives

6.11.13

Sean working on the arch cladding

10.10.13

Arch doors are hung

2.10.13

Assembly starts of the kitchen

23.09.13

Checking the kitchen at the sprayers

11.09.13

1st floor is sanded

18.07.13

Progress on the 1st floor continues

12.07.13

1st row of oak floor is laid

11.07.13

Hall get plastered

10.07.13

Vitsœ shelving goes up in garden room

5.07.13

Garden room is finished

2.07.13

Garden room is painted

28.06.13

Glass openings get adjusted and bonded

11.03.13

Ceiling is finished

10.03.13

Bedroom becomes new temporary kitchen

9.03.13

Old kitchen gets ripped out

7.03.13

New bedroom floor is laid

6.03.13

New doors arrive and get hung

5.03.13

They start painting the 1st floor ceiling

4.03.13

Back wall in the upstairs toilet gets bonded

2.03.13

We uncover Buzz lightyear!

1.03.13

Final Erco lights get fixed and the last holes are filled

28.02.13

Back stairs slope gets plaster boarded

27.02.13

New bedroom floor gets laid

26.02.13

New bedroom wall gets painted

25.02.13

Utility room gets final coat of paint

22.02.13

New Erco lights get tested

20.02.13

Lee’s stilts

19.02.13

New 1st floor w/c get plastered

18.02.13

New w/c and entrance to plant room take shape

15.02.13

Oak beams replace steel lintels above Bar Lane windows

14.02.13

Slope created on back stairs

13.02.13

1st floor ceiling gets filled

12.02.13

Utility room gets a coat of paint

4.02.13

Old wood burner flue hole get plasterboarded up

1.02.13

Work on the 1st floor ceiling lights start

31.01.13

Back stairs gets its 1st floor wall

30.01.13

Back staircase gets plastered up to handrail height

29.01.13

Hallway walls and ceiling get plastered

28.01.13

Utility room gets plastered

26.01.13

Having fun

25.01.13

New bedroom ceiling gets plasterboarded

24.01.13

Fire proof plasterboard in the utility room

23.01.13

Plasterboarding of the new bedroom wall

22.01.13

Work on the back stairs starts

21.01.13

1st floor ply completed

18.01.13

Chicken wire in new utility room wall

17.01.13

Calculations

16.01.13

More snow

15.01.13

Snow starts

14.01.13

Ply arrives

11.01.13

Flooring finish tests

10.01.13

Where the back stairs will be

9.01.13

New entrance to under stairs cupboard

8.01.13

New hallway

7.01.13

Utility room takes shape

18.12.12

1st floor oak flooring test

17.12.12

Utility floor screed and temporary ply in new bedroom

15.12.12

Utility room underfloor heating is finished

14.12.12

New opening

13.12.12

New bedroom floor screed

10.12.12

New walls start to take shape

7.12.12

Plumbers finish upstairs

30.11.12

Wall and floor remains

29.11.12

Wood burner flue comes down

28.11.12

Plumbers start

27.11.12

Old arch comes down

26.11.12

Wall down, floor up

25.11.12

Messing around before the floor comes up

23.11.12

Scaffold to remove the wood burner chimney

22.11.12

New services start going in

 

21.11.12

What a mess

20.11.12

New back stairs opening

19.11.12

Architects plans

13.11.12

Hall voids get a temporary cover

8.11.12

Rockwool and Vermiculite

27.09.12

Ground floor slab

21.09.12

Carpet comes up

20.09.12

New stud wall goes up

18.09.12

Work started…